Mud and tape on a Saturday. The team was cranking today.

The electrical was completed today, less a few items we plan to run up thru the floor. I learned that “tails” essentially means wires leading to a “fixture / outlet”. After drywall is completed, the “tails” are located and pulled thru to the appropriate fixture / outlet.

I’m back at work. Lots of goodness happening throughout the day… the tub was installed. I managed to get to the house around 5, right before sundown. It’s a little darker in the house since we’re facing east.

This day was a bit crazy… framing, plumbing, mechanical, and electrical was underway at once. Can be a bit tricky in a 850 sq ft house.

I pulled up this morning to find a truckload of concrete from the basement. Old concrete is a bit tough to demo. What was initially scoped to be a day of work turns into 3… aye!